Late Payment Interest In Construction: What The Rate Is In 2026 And How It's Set
When the Bank of England changes interest rates, many businesses assume the interest they can charge on a late payment changes with it straight away. It doesn't work quite like that, and the detail affects what you can claim, particularly in construction, where payments can be overdue for months.
In short: statutory late payment interest on business-to-business debts is 8% above the Bank of England base rate, but it uses the base rate on a fixed reference date, not today's. For invoices that became overdue in 2026, the rate is 11.75%. The Bank Rate rise to 4% on 5 November doesn't change that, but it feeds into the rate for debts that become overdue from 1 January 2027.
How The Rate Is Set
Under the Late Payment of Commercial Debts (Interest) Act 1998, statutory interest is 8% above the Bank of England base rate. The base rate used is the one in force on a reference date: 30 June for interest starting between 1 July and 31 December, and 31 December for interest starting between 1 January and 30 June. Once the rate is set, it stays locked for as long as that debt remains unpaid.
What The Rate Is In 2026
Bank Rate was 3.75% on both of the reference dates that apply to debts becoming overdue in 2026, so statutory interest on those invoices is 11.75% (3.75% plus 8%).
What Changed On 5 November
The Bank of England's Monetary Policy Committee voted 8 to 1 to raise Bank Rate from 3.75% to 4%. That doesn't change the rate on invoices that are already overdue, because the rate is locked. It also doesn't change the rate for debts that become overdue before the end of December, because those use the 30 June reference rate.
What Happens From 1 January 2027
Debts that become overdue between 1 January and 30 June 2027 will use the base rate on 31 December 2026. If Bank Rate is still 4% that day, statutory interest on those debts will be 12%. The Bank's next decision is on 17 December, so the figure isn't confirmed until then.
How Interest Is Calculated
Interest is simple rather than compound, and it builds up daily from the date payment was due until the invoice is paid:
Invoice amount x (8% + base rate) ÷ 365 x number of days late
A worked example: the following is for illustration. A £10,000 invoice paid 60 days late at 11.75% accrues about £193.15 in interest. Add £100 in fixed compensation and the debtor owes roughly £293.15 on top of the invoice. The same invoice at 12% would accrue about £197.26.
What Else You Can Claim
Interest is only part of it. You can also claim fixed compensation per overdue invoice (£40 for debts under £1,000, £70 for debts from £1,000 to £9,999.99, and £100 for debts of £10,000 or more), plus reasonable recovery costs where they exceed the fixed amount.
Interest In Construction Contracts
In construction, the date payment is due depends on the contract's payment mechanism, so the starting point for interest is the contractual due date, not the date of the work. Standard forms such as JCT and NEC come with their own payment provisions, and some include their own late payment terms, so check what your contract says before you calculate a claim.
Overdue retentions are payments that have fallen due like any other, so interest can often be claimed from the release date. A genuine dispute over an application can affect your entitlement until it's resolved, which is another reason to keep your applications, valuations and certificates in order.
When Statutory Interest Might Not Apply
A contract that provides its own substantial remedy for late payment can replace statutory interest. It's sensible to refer to interest in your terms and on your invoices, and to tell a client in writing that you intend to claim it.
What's Changing
The Commercial Payments Bill, also known as the Late Payments Bill, would make statutory interest mandatory, with a 60-day cap on payment terms and, in Great Britain, a ban on withholding construction retentions. It has passed the House of Lords and is awaiting its Commons stages. If it's approved, it's expected to come into force in 2027, so the current rules still apply.
Don't Leave It On The Table
Interest and compensation are legitimate parts of a late payment claim, and plenty of businesses never claim them. If you have overdue invoices or retentions that a client has stopped responding to, specialist construction debt recovery can help you pursue what you're owed, including interest and costs where they're due.
This article provides general information only and isn't legal advice. It will be updated when the Bank of England announces its next decision.
FAQs
What is the late payment interest rate in 2026? For invoices that became overdue in 2026, it's 11.75%: 8% above a base rate of 3.75% on the reference dates.
Does the Bank Rate rise change the interest on my overdue invoices? No. The rate is locked on the reference date and stays fixed for that debt. The rise affects debts that become overdue from 1 January 2027, depending on the base rate on 31 December.
How is late payment interest calculated? As simple interest, charged daily from the due date: invoice amount x (8% + base rate) ÷ 365 x days late.
Can I claim interest on an overdue retention? A retention that has fallen due and hasn't been paid is an overdue payment, so interest can often be claimed from the release date, unless a genuine dispute or the contract's own terms change the position.
What if my contract sets its own late payment rate? A contract that provides a substantial remedy for late payment can replace statutory interest, so check your terms.